From proposal to completed home

What happens at each stage, who decides, and why an approval is not a home.

A council vote makes the news. It is one step of about eight, and the homes come years later, if at all.

An independent explainer by Raj Oberoi, not legal advice. Checked against the law and each City's pages on November 18, 2026.

The short version

Approved is not built

  1. Application

    City staff

  2. Council: readings and, sometimes, a public hearing

    Council

  3. Conditions, then final adoption

    Council and the owner

  4. Building permit

    City building staff

  5. Construction

    The builder

  6. Occupancy

    City building staff

Each City's process has its own names and order for some steps, and not every project needs every step. A house on an already-zoned lot may go straight to a building permit.

Step by step

Eight stages, opened one at a time

1. Idea and early advice

Who decides: The owner

An owner or developer talks to City planners before applying. Surrey has a formal pre-application step.

Is it counted? Not counted anywhere.

Official source

2. Application

Who decides: City staff

The owner applies to rezone, for a development permit, a variance, a subdivision, or a mix. Staff check it against the Official Community Plan and other policies, and refer it to other departments and agencies.

Is it counted? Listed by each City as "in process".

Official source

3. Council: readings and, sometimes, a public hearing

Who decides: Council

A rezoning is a bylaw. Council votes on it at first, second and third reading. If a hearing is required, it is held after first reading and before third. Residential rezonings that fit the plan no longer get a hearing.

Is it counted? Covered in Council Watch.

More on this

4. Conditions, then final adoption

Who decides: Council and the owner

Between third reading and adoption, the owner meets the City's conditions: servicing agreements, fees and charges, legal agreements. Then Council adopts the bylaw. This can take months.

Is it counted? Surrey lists rezonings "at third reading" and "final approvals".

Official source

5. Development permit

Who decides: Council or staff

In designated areas, a development permit sets the form and character of the building. Variances to the rules need a development variance permit.

Is it counted? Surrey lists development permits in process and issued.

Official source

6. Building permit

Who decides: City building staff

Plans are checked against the B.C. Building Code and the City's bylaws. This is when homes start to be counted in monthly permit figures.

Is it counted? Counted monthly by both Cities.

More on this

7. Construction

Who decides: The builder

Work on site, with inspections along the way. Timing is largely in the builder's hands, and some permitted projects stall. Surrey's own report to Council says the construction timeline after a permit is "largely outside of the City's control."

Is it counted? Not published by either City.

Official source

8. Occupancy

Who decides: City building staff

An occupancy permit says people can move in. Completed homes minus homes demolished are the "net new" homes reported to the Province each year.

Is it counted? Counted yearly, for the Province.

More on this

Why it matters

Three reasons approved homes don't appear

  • Conditions take time. Third reading is not adoption. The owner may take months to meet the City's conditions, or never do.
  • Permits are not construction. A building permit is permission, not an obligation to build.
  • Construction is the owner's timeline. Financing, costs and the market decide when shovels go in.

Sources: Local Government Act, sections 464 and 465 (public hearings); City of Surrey, Land Development Application Process; City of White Rock, Development; City of Surrey, Corporate Report R145.